    Bathroom Remodeling · Seattle, WA

    Bathroom Remodel with Heated Natural Stone Flooring in Magnolia, Seattle

    In progress

    Dan and Kristen Petchnick wanted to update an existing bathroom in Seattle's Magnolia neighborhood while keeping its general layout.

    Bathroom with tiled tub surround, window and toilet.

    Project: Bathroom remodel with tub and shower renovation, natural stone tile, and electric heated flooring

    Client: Dan and Kristen Petchnick

    Location: Magnolia, Seattle, WA 98199

    Floor: Natural stone tile in a centered brick-lay pattern over electric heating

    Heated-Floor Inspection: Electrical inspection passed on August 5, 2026

    Vanity: Homeowner-supplied vanity with integrated lighting

    Additional Work: New water heater, mechanical-room sliding doors, closet-wall and ceiling repairs

    Work Period: July-September 2026

    Project Status: In progress

    Contents
    1. The Homeowners' Goals and Remodeling Plan
    2. Site Protection, Demolition, and Preparation
    3. Heated Bathroom Floor Installation and Electrical Inspection
    4. Bathroom Floor Tile Layout and Installation
    5. Shower Tile Layout, Window Trim, and Recessed Niche
    6. Bathtub, Shower Valve, and Plumbing Connections
    7. Vanity Installation and Existing Plumbing Misalignment
    8. Fitting the Vanity Against an Uneven Wall
    9. Coordinating the Vanity's Integrated Lighting
    10. Mirrors, Accessories, and Fixture Alignment
    11. Mechanical Room Improvements
    12. September 1 Homeowner Walkthrough and Detailed Punch List
    13. Closet Wall and Bedroom Ceiling Repairs
    14. Natural Stone Floor Finishing and Care
    15. September 17 Finishing Work and Cleanup
    16. September 29 Final Stone Touch-Up
    17. Quality Control and Remaining Adjustments
    18. Project Results

    Dan and Kristen Petchnick wanted to update an existing bathroom in Seattle's Magnolia neighborhood while keeping its general layout. The renovation included a replacement bathtub and shower, a heated natural stone floor, wall tile, a vanity with integrated lighting, updated plumbing and electrical work, improved ventilation, and associated drywall and finish carpentry.

    The existing bathroom presented several challenges for the new installations. Framing inside the walls limited the available space for vanity plumbing, while the homeowners' vanity required additional electrical connections for its integrated lighting. We also needed to coordinate the shower tile, recessed niche, plumbing fixtures, and surrounding finishes within the existing layout.

    The heated-floor electrical installation passed inspection on August 5, 2026, and we completed the natural stone floor tile and grout on August 7. Bathroom finishing continued through September, alongside repairs to the adjoining closet wall and bedroom ceiling. By September 29, we had completed another stone-floor touch-up, while final project closeout remained ahead.

    The Homeowners' Goals and Remodeling Plan

    Dan and Kristen wanted to update their Magnolia bathroom while keeping its existing layout. They selected natural stone tile for the floor and walls, along with a vanity featuring integrated lighting. Their plans also included a replacement bathtub and shower, electric floor heating, updated plumbing fixtures, and improved ventilation.

    The homeowners supplied many of the visible materials, including tile, plumbing fixtures, and the vanity. Our work involved preparing the bathroom for those selections, coordinating the plumbing and electrical connections, installing the new finishes, and making adjustments where the existing wall construction affected the planned layout.

    The renovation also extended into the adjoining mechanical room, where we installed a new water heater, and included repairs to a nearby closet wall and bedroom ceiling.

    Site Protection, Demolition, and Preparation

    The bathroom renovation involved removing existing fixtures and finishes while protecting the adjoining rooms. We used temporary dust barriers and floor coverings to separate the construction area from the rest of the home.

    On August 11, we reinforced the dust barrier between the bathroom and the main house. We used similar protection during the September closet and ceiling repairs to keep construction dust away from the bedroom. By September 17, the scheduled cleanup was complete, and the temporary floor and entryway coverings had been removed.

    Heated Bathroom Floor Installation and Electrical Inspection

    The heated floor had to be installed and inspected before the final tile assembly covered it. During the August 3 coordination, the team reviewed installation and the upcoming inspection, and an additional Schluter floor-heating sensor was delivered on August 4. On August 5, the heated-floor electrical installation passed inspection, allowing the team to proceed with the remaining floor work.

    Bathroom Floor Tile Layout and Installation

    On August 7, the team reviewed the floor layout with the installer. The selected installation was a centered brick-lay pattern, which balances the cuts around the room and avoids narrow pieces along one side. Floor tile installation and grouting were completed that day, and the wall and floor tile had been pre-sealed.

    Shower Tile Layout, Window Trim, and Recessed Niche

    During our August 3 and 4 walkthroughs, we reviewed the shower-wall tile layout, grout spacing, and finishing details around the existing window. Dan and Kristen approved a full bullnose tile border around the window, with tile extending into the interior returns. We also planned the tile layout around the bathroom doorway to keep the cuts balanced.

    The shower design included a recessed niche for soap and other essentials. Its installation required additional work within the prepared shower wall, including attention to the surrounding waterproofing and tile. By August 17, the niche had been finished and the shower-wall grouting completed.

    Bathtub, Shower Valve, and Plumbing Connections

    The bathroom plumbing updates included the bathtub and shower connections, faucets, toilet, and vanity plumbing. By August 14, the toilet and faucets had been installed, with additional plumbing trim and drain connections continuing through the month.

    During our August 17 review, we found that the shower valve was positioned too deeply inside the wall for the selected trim. We worked with the plumbing contractor on an adjustment to the valve assembly, with final operation of the shower still requiring attention.

    On August 25, we also completed a separate finishing correction around the shower drain, including its color and sealant.

    Vanity Installation and Existing Plumbing Misalignment

    Installing the homeowners' vanity required adjustments to the existing plumbing layout. On August 11, we found that the water supply and drain connections did not align with the planned sink positions. Framing and backing inside the wall limited how far the pipes could be moved.

    Rather than changing the vanity's intended position, we planned to adjust the final drain connections during plumbing trim-out. The goal was to accommodate the existing framing without changing the homeowners' selected vanity layout.

    Fitting the Vanity Against an Uneven Wall

    The new vanity also required careful fitting against the existing wall and base molding. We planned to notch the molding around the vanity legs rather than cut or shorten the legs themselves. After reviewing the trim with Dan and Kristen on August 13, we prepared replacement molding on August 14 to better match the room's existing finishes.

    The adjoining wall was not square, which left a gap where the vanity backsplash met the wall. We reviewed options for a fitted side splash or trim piece that could accommodate the uneven surface without changing the vanity position. The permanent side splash remained a separate finishing item as the bathroom renovation approached completion.

    Coordinating the Vanity's Integrated Lighting

    The homeowners' vanity included integrated lighting that needed its own electrical connections behind the cabinet. From August 6 through August 10, we reviewed the wall framing, plumbing, and wiring to determine where the outlets and switches could fit without interfering with the vanity.

    By August 19, the vanity's integrated lighting was connected and tested. We also identified a plug-clearance issue that affected one of the vanity drawers and planned a lower-profile connection to address it. The bathroom exhaust fan and overhead light were operating on separate switches by August 13.

    Mirrors, Accessories, and Fixture Alignment

    On August 11, the team reviewed mirror and accessory locations with Dan. The mirrors were positioned to align with the sink centers, two towel bars were discussed at about 50 inches to center, and the toilet paper holder location was reviewed. On August 13, Dan reviewed concerns originally raised by Kristen. The vanity lights were mounted at different heights and were not centered, the towel bars were not level, and the toilet paper holder was not square. On August 25, vanity-light alignment was still outstanding, and the September 1 walkthrough rechecked trim and grab bars. We do not have final confirmation of every light and accessory.

    Mechanical Room Improvements

    The remodel also included work in the adjoining mechanical room. We installed a new water heater on August 5 and reinstalled the sliding doors to restore access to the mechanical area.

    September 1 Homeowner Walkthrough and Detailed Punch List

    On September 1, Leonardo, Alex, Vlad, Dan, and Kristen reviewed the bathroom and remaining work using homeowner-submitted photographs. The walkthrough covered the adjacent closet, natural-stone floor, air duct, vanity, shower tile, backsplash, accessories, trim, and drywall. The homeowners identified marks on the stone floor, which the team assessed as likely removable scuffs rather than deep scratches. A hazy sealer area was visible under low light, and the proposed correction was to strip and reseal the affected stone.

    The team also found insulation and debris in the air duct and planned to clean it. A wall scrape beneath the vanity needed drywall repair, and shower pencil-liner edges, tile transitions, and fixture penetrations needed sealant cleanup. Paintable caulking was selected where the tile meets the ceiling and painted walls. The September 1 walkthrough did not establish completion. It set out a correction plan.

    Closet Wall and Bedroom Ceiling Repairs

    During our September 1 walkthrough, we inspected a crack in the closet wall adjoining the bathroom. When we opened the affected area on September 14, we found loose shiplap, cracked plaster, damaged mesh, and unstable edges. A small surface patch would not have addressed the condition underneath, so we expanded the repair area and used new sheet material and additional support.

    We also repaired a crack in the nearby bedroom ceiling and damaged drywall beneath the vanity. By September 17, the drywall texture and primer were complete. Dan and Kristen chose to handle the final painting themselves.

    Natural Stone Floor Finishing and Care

    Natural stone needed additional attention during the final finishing stages. During our September walkthroughs, we reviewed surface marks and areas where the sealer appeared uneven, then planned targeted cleaning and resealing rather than replacing the installed tile.

    On September 17, we cleaned the bathroom floor and resealed three affected tiles. One remaining surface mark was addressed during our September 29 follow-up visit.

    September 17 Finishing Work and Cleanup

    By September 17, we had finished the scheduled repairs and removed the temporary floor and entryway protection. We cleaned the bathroom tile and resealed three affected natural stone tiles before clearing the work areas. Dan and Kristen planned to handle the final painting themselves, while the permanent vanity side splash remained a separate finishing item.

    September 29 Final Stone Touch-Up

    On September 29, Leonardo returned to address the final visible scuff on the natural-stone tile. He treated the area, removed the remaining mark, checked the surface from several angles, and removed excess product so no residue showed. No further scuff was visible during his inspection. Dan reviewed the result with Leonardo and was advised to avoid the treated area for at least one hour. Leonardo also explained how to reseal porous natural stone in the future, including removing excess sealer before it dries and streaks. Photographs and a short video documented the visit.

    Quality Control and Remaining Adjustments

    During our September 1 walkthrough, Dan and Kristen reviewed the bathroom finishes with us, including the natural stone flooring, shower tile, vanity, and surrounding trim. We identified areas needing further attention and returned throughout the month to complete the finishing work.

    By September 17, we had completed the scheduled drywall repairs, tile cleaning, selective resealing, and site cleanup. On September 29, we removed the last visible scuff from the natural stone, and Dan reviewed the result onsite.

    The bathroom was approaching its final closeout stage, with the permanent vanity side splash and final shower-valve adjustments still to be resolved. The project remained in progress.

    Project Results

    Dan and Kristen's Magnolia bathroom has undergone substantial improvements while retaining its original layout. The new natural stone floor features a centered brick-lay pattern over an electric heating system that passed its electrical inspection on August 5, 2026. Tile installation and grouting were completed on August 7, bringing the selected stone finish into the remodeled bathroom.

    The updated space also includes a recessed shower niche, new plumbing fixtures, a vanity with connected integrated lighting, and a bathroom exhaust fan and light operating on separate switches. We installed a new water heater in the adjoining mechanical room and completed repairs to the nearby closet wall and bedroom ceiling.

    During September, we worked through additional finishing details on the tile, grout, drywall, and natural stone surfaces. The last visible scuff on the stone floor was removed on September 29, and Dan reviewed the result with us.

    The renovation remained in progress at the end of September, with the permanent vanity side splash, final shower-valve work, and homeowner walkthrough among the remaining steps.