    Whole-Home Remodeling · Seattle, WA

    Multi-Room Home Remodel in Seattle, WA

    In progress

    Yulana Shastak planned a multi-room renovation of her Seattle home, with major changes to the primary and kids' bathrooms, new flooring, updated doors and windows, fireplace improvements, and interior finishing work.

    Living room painting work with protected flooring and a row of large windows.

    Project: Multi-room remodel with two bathrooms, hardwood, carpet, fireplace work, and interior finishing

    Client: Yulana Shastak

    Location: Seattle, WA 98109

    Primary Bathroom: Custom vanity and countertop, freestanding tub, shower pony wall, mosaic floor, and shower glass

    Kids' Bathroom: Tub-to-shower conversion with a curb, three niches, new vanity, and glass door

    Flooring: Hardwood in the hallway and downstairs, carpet in the bedrooms

    Additional Work: Fireplace paint and custom doors, interior doors and hardware, stair handrails, interior painting

    Work Period: April 2026-present

    Project Status: In progress

    Contents
    1. The Homeowner's Goals and the Original Home Conditions
    2. Homeowner-Supplied Materials and Coordination With Outside Contractors
    3. Initial Demolition and Kids' Bathroom Framing
    4. Primary Bathroom: Custom Countertop, Lower Shelf, and Vanity
    5. Primary Bathroom Pony Wall, Floor Leveling, and Mosaic Tile
    6. Primary Shower Pan and HydroBlok Waterproofing
    7. Freestanding Bathtub and Plumbing Installation
    8. Primary Bathroom Windows and Shower Glass
    9. Kids' Bathroom: Converting the Tub to a Walk-In Shower
    10. Hardwood Flooring in the Hallway and Downstairs Areas
    11. Bedroom Carpeting and the Installation Schedule
    12. Interior Doors, Hardware, and Finish Carpentry
    13. Fireplace Surround, Painting, and Custom Glass Doors
    14. Kitchen Backsplash, Living-Area Drywall, and Wall-to-Tile Transitions
    15. Bathroom Paint Colors and Finish Specifications
    16. Interior Painting Preparation in the Main Living Areas
    17. Quality Control and Remaining Adjustments
    18. Project Results

    Yulana Shastak planned a multi-room renovation of her Seattle home, with major changes to the primary and kids' bathrooms, new flooring, updated doors and windows, fireplace improvements, and interior finishing work. She selected and supplied many of the visible materials, including tile, hardwood, carpet, plumbing fixtures, doors, and lighting, so an important part of the project was coordinating those selections with the existing spaces and installation schedule.

    Alta Group Remodeling helped organize the work across several areas of the home, including bathroom reconstruction, flooring installation, finish carpentry, and coordination with specialty contractors. Because work was taking place in multiple rooms, the construction sequence had to account for how drywall, flooring, plumbing, glass, and painting affected one another.

    The renovation began with the kids' bathroom framing, completed on April 3, 2026. Hardwood flooring was installed by June 1, and the primary bathroom's freestanding tub, sink, and faucet were in place by August 10. Bathroom finishing, carpeting, shower glass, and fireplace improvements continued through September and October. By October 22, finish coats had been applied to prepared walls and ceilings throughout the main living areas, with final paint touch-ups and cleanup still ahead.

    The Homeowner's Goals and the Original Home Conditions

    Yulana wanted to make significant updates throughout her home while selecting many of the finishes and fixtures herself. The primary bathroom design included replacing the existing tub and shower arrangement with a freestanding bathtub, a remodeled shower, a custom vanity and countertop, new tile, and updated windows. The kids' bathroom was planned around converting the existing bathtub into a walk-in shower with a curb. The design also called for three recessed shower niches, a new vanity, mosaic flooring, wall tile extending to the ceiling, and a glass shower door.

    Beyond the bathrooms, the renovation included hardwood flooring in the hallway and downstairs areas, new carpeting in the bedrooms, selected door and window changes, fireplace improvements, and interior painting. Coordinating these updates across multiple rooms was an important part of the project.

    Homeowner-Supplied Materials and Coordination With Outside Contractors

    Yulana supplied many of the materials used throughout the renovation, including windows, plumbing fixtures, tile, hardwood, carpet, doors, and lighting. We coordinated installation requirements and schedules around these selections while working with the specialty contractors involved in the project.

    The sequence mattered because several installations depended on earlier work. Upstairs carpeting needed to follow dusty drywall repairs, shower glass installation depended on the bathroom tile and surrounding finishes, and the fireplace improvements required coordination with the custom door supplier. Planning these stages helped the project move forward while work continued in different parts of the home.

    Initial Demolition and Kids' Bathroom Framing

    The original plan called for removing existing bathroom components and preparing the wall and floor assemblies for the new layouts. In the kids' bathroom, that meant removing the old bathtub and preparing for a walk-in shower with a curb. By April 3, the initial demolition and framing work for the kids' bathroom had been completed, establishing the new shower layout for the next stages of construction.

    Primary Bathroom: Custom Countertop, Lower Shelf, and Vanity

    The primary bathroom was not planned around a conventional replacement vanity. The estimate included a tile-ready countertop with a sink cutout, a lower shelf beneath it, and cabinet covers, all coordinated with the surrounding tile. During our June planning discussions, we reviewed the vanity opening with Yulana. On June 11, the design direction was confirmed: the vanity would include a solid panel matching the approved drawing rather than a conventional cabinet door.

    Primary Bathroom Pony Wall, Floor Leveling, and Mosaic Tile

    The original plan called for converting the wall between the shower and the main bathroom area into a pony wall, a homeowner-requested change that needed to be coordinated with the shower pan, waterproofing, tile layout, and glass enclosure. The estimate also included about 80 square feet of floor preparation with self-leveling compound, coordinated to a finished-floor height of about ¾ inch, and about 76 to 80 square feet of homeowner-supplied mosaic tile with a Schluter transition at the doorway.

    On October 2, our crew cleaned up the grout and refined the transitions where the bathroom tile meets the surrounding walls. This finishing work helped create cleaner edges between the tiled surfaces and painted drywall.

    Primary Shower Pan and HydroBlok Waterproofing

    The primary shower renovation included a planned HydroBlok shower pan covering approximately 13.5 square feet, along with extensive wall preparation for tile and waterproofing. The design required coordination between the shower pan, wall panels, sealed joints, niche details, and eventual glass enclosure. These installation stages progressed through the summer of 2026, with shower glass work continuing into the fall. The waterproofing and tile assemblies needed to be coordinated with the finished shower dimensions and glass installation requirements.

    Freestanding Bathtub and Plumbing Installation

    The plumbing work included disconnecting the old bathtub, preparing new water supply and drain connections, and fitting the homeowner-supplied freestanding tub, vanity fixtures, and shower trim. The plan also called for reinstalling the existing toilet. By August 10, we had installed the freestanding tub, sink, and faucet in the primary bathroom, while other plumbing connections and finishing work continued.

    Plumbing finishing continued through August, including connections and sealant around the new bathtub, sinks, and toilets. On August 20, we worked through additional fixture and drain connections in both bathrooms, coordinating the remaining plumbing details with the new installations.

    Primary Bathroom Windows and Shower Glass

    The primary bathroom design included three homeowner-supplied windows and a glass shower enclosure approximately 4 feet 6 inches wide by 7 feet high. Installing the glass required coordination with the completed tile surfaces, shower dimensions, and approved door hardware.

    Shower glass installation progressed through August, with adjustments to the hardware and final fitting continuing into October. The glass installation was inspected and approved on October 8, bringing the enclosure work to a close while other bathroom finishes continued.

    Kids' Bathroom: Converting the Tub to a Walk-In Shower

    The kids' bathroom plan included new mosaic floor tile, wall tile from floor to ceiling, a new vanity and countertop, window replacement, and shower glass. By August 10, we had completed the tile work around the kids' bathroom vanity and added a third shower niche to match the two lower ones. This adjustment gave the shower three matching niches while keeping the tile layout consistent.

    The kids' bathroom also included custom shower glass and new vanity mirrors. We measured the mirrors on August 12 and installed them by August 27. The shower glass required additional coordination to fit the door hardware and surrounding tile. On October 7, Emerald City Glass adjusted the shower door to align with the finished tile surfaces. The shower glass work was inspected and approved on October 8.

    Hardwood Flooring in the Hallway and Downstairs Areas

    The flooring renovation included replacing sections of hallway carpet with hardwood and installing new hardwood in the downstairs areas. Yulana supplied the flooring, and we coordinated the installation around existing doorways, wall openings, and stair transitions. Daniel completed the hardwood installation on June 1, giving the hallway and downstairs spaces their new flooring well before the later bathroom and interior finishing work.

    Bedroom Carpeting and the Installation Schedule

    The bedroom updates included new carpeting, baseboards, windows, and modifications to selected door openings. Because drywall repairs were still underway upstairs, we coordinated the carpet installation around that work to help protect the new flooring from construction dust and damage.

    The carpet and padding arrived on August 20. Once the nearby drywall work was ready, we cleaned the upstairs rooms on September 2 to prepare for installation. On September 7, the new carpet was installed in the primary and kids' bedrooms, replacing the previous floor coverings as part of the wider interior renovation.

    Interior Doors, Hardware, and Finish Carpentry

    The renovation also included updated interior doors, hardware, and finish carpentry around the modified openings. On September 1, we installed hinges, doorknobs, handles, and bathroom accessories, with the door hardware work completed and approved by September 4. Additional finishing continued through September, including door stops, surrounding trim, and bathroom accessories. We coordinated these installations with the other contractors working in the home so the details would fit the updated spaces.

    During our October 1 walkthrough, we also reviewed the wood entry door and its long black pull handles. The door still needed a final adjustment check, and by October 13, it was closing properly. The wooden stair handrails were another part of the interior updates. We reviewed their design with Yulana in early October, and she approved the installed handrails on October 13. The final clear-coat finish was the next step, with the sheen still to be selected.

    Fireplace Surround, Painting, and Custom Glass Doors

    The fireplace updates included a new tile surround, painting, and planned custom glass doors. Painting was completed on September 2, and our September 4 inspection confirmed that the finish was complete.

    The custom glass doors presented an additional challenge when the metal frames arrived damaged. During our September 15 inspection, we found bent and misaligned sections that prevented the doors from being installed as intended. We began coordinating replacements with the supplier, while the completed fireplace painting remained in place. The replacement doors were still pending as the project moved into its final interior finishing stages.

    Kitchen Backsplash, Living-Area Drywall, and Wall-to-Tile Transitions

    The kitchen backsplash used homeowner-supplied solid-surface material. During our August 10 review, we identified a gap between the installed backsplash and the adjoining wall that required drywall finishing rather than a simple caulk joint. We reviewed the surrounding kitchen and living-area surfaces on August 17 to determine the appropriate repair approach.

    The bathrooms also required careful finishing where tile met painted drywall. On August 26, we reviewed the kids' bathroom wall transitions and identified additional surface preparation. By October 2, the upstairs bathroom walls and ceilings had been painted, and the team had completed grout cleanup and additional detailing around the tile-to-wall transitions.

    Bathroom Paint Colors and Finish Specifications

    Yulana selected Benjamin Moore China White OC-141 for the upstairs bathroom finishes. In the kids' bathroom, she chose Scuff-X in a satin finish for the walls, while the ceilings in both bathrooms use China White ceiling paint in a flat finish. These selections keep the ceiling color consistent between the two bathrooms while allowing a different sheen on the kids' bathroom walls.

    Interior Painting Preparation in the Main Living Areas

    Interior painting progressed through several stages in October. On October 16 and 17, we continued repairing drywall, patching ceiling seams, and preparing the walls around windows, door frames, and built-in cabinetry. We protected the hardwood flooring, kitchen cabinets, countertops, and lighting while working through these areas.

    By October 19, the crew had begun applying primer and paint to prepared surfaces. On October 22, finish coats were being applied throughout the kitchen, living room, dining area, and hallway. We also began removing window masking in areas where painting had progressed. The living room walls and ceilings were substantially finished, while detailed work continued around doors, windows, baseboards, and ceiling transitions. With most of the major painting underway or substantially finished, our next steps were to complete the remaining touch-ups, remove the protective coverings, and clean the rooms.

    Quality Control and Remaining Adjustments

    As the larger installations came together, we worked through the remaining finishing details across the home. After the bedroom carpeting was installed, several doors and trim pieces needed repairs. We returned to fill, sand, and repaint the affected areas, completing those corrections by September 20.

    In October, the kids' shower door was adjusted to fit the surrounding tile, and Yulana approved the wooden stair handrails. The custom fireplace doors still required replacement after the original frames arrived damaged, while the final handrail clear coat remained to be selected.

    By October 22, the renovation had reached an advanced finishing stage. The main bathroom and flooring improvements were largely in place, and painting in the kitchen, living room, dining area, and hallway was nearing completion. We were continuing with final paint touch-ups, removal of protective coverings, and cleaning before the remaining work could be finished.

    Project Results

    By October 22, 2026, Yulana's Seattle home had undergone major changes across its bathrooms, bedrooms, hallways, and living areas. The primary bathroom had received a freestanding bathtub, sink, and faucet, along with extensive tile work and a custom vanity design. The shower glass installation was approved on October 8, bringing another major part of the bathroom renovation to completion.

    In the kids' bathroom, we converted the former bathtub area into a walk-in shower with a curb, three recessed niches, and new tile finishes. The vanity mirrors were installed by August 27, and the shower door was adjusted to fit the surrounding tile on October 7. Painting of the upstairs bathroom walls and ceilings was completed in early October, followed by additional touch-ups around the tile-to-wall transitions.

    We finished the hardwood flooring in the hallway and downstairs areas on June 1. New carpet was installed in the primary and kids' bedrooms in September, and the interior updates also included new door hardware, fireplace painting, and finish carpentry. Yulana approved the wooden stair handrails on October 13.

    The kitchen, living room, dining area, and hallway had reached the final painting stages by October 22. Finish coats had been applied to prepared walls and ceilings, and we had begun removing protective coverings from painted areas. The living room was substantially finished, with additional detail work continuing elsewhere.

    The remodel was still underway as of October 22. Remaining work included paint touch-ups, cleaning, the final handrail finish, and coordination of the custom fireplace doors.