Tamra wanted to update both bathrooms in her fifth-floor Seattle condominium with low-profile curbless showers and new tile finishes. Her remodeling plans also included porcelain tile in the entryway, creating a coordinated update across several areas of the home. The existing bathroom floors presented an unusual challenge. Beneath the old tile was gypcrete containing hydronic heating tubing, and sections of that material had become unstable during tile removal. Our approach required carefully removing the damaged gypcrete, protecting the embedded heating lines, and rebuilding the floor assemblies to accommodate the new shower pans. We also needed to adapt the guest bathroom shower to an existing drain that did not align with the planned pan.
We began with a detailed site walkthrough on October 6, 2026. On October 12, our crew removed the unstable gypcrete, and by October 13, we had completed the self-leveling work and installed both shower pans. Additional floor and waterproofing preparation continued on October 14. The project remained in progress, with tile installation, final waterproofing verification, and the homeowner walkthrough still ahead.
The Homeowner's Goals and Existing Bathroom Conditions
Tamra's renovation plan included two curbless showers with low-profile HydroBlok pans, center drains, tileable drain covers, and waterproof wall systems. She also selected new tile finishes for the bathrooms and planned porcelain tile for the condominium entryway. The primary bathroom required extensive floor preparation because hydronic heating lines were embedded in the existing gypcrete. The original plan called for removing unstable material and rebuilding the floor with self-leveling underlayment and a membrane suitable for the tile assembly. The guest bathroom initially required less extensive floor work, but conditions uncovered during preparation ultimately changed that approach.
Because the project involved existing plumbing and hydronic heating, we also needed to coordinate the shower drain connections with the homeowner's plumber while protecting the heating system during demolition and floor reconstruction.
October 6 Walkthrough: Measurements, Elevations, and Drain Locations
During our October 6 walkthrough, we reviewed both bathroom layouts with Tamra and measured the existing shower openings, floor elevations, and locations of the hydronic heating lines. The existing floor assembly was approximately 1½ inches thick, which created an important constraint for the curbless shower design. The shower pans, leveling compound, membranes, mortar, and tile all needed to fit within the available floor height while maintaining the intended transitions between the showers and surrounding bathroom floors.
The primary shower opening measured approximately 37 inches by 4 feet 11 inches. We reviewed the shower pan orientation, drain position, and entry location to determine how the new assembly would fit within the existing space. The team also considered adjusting the slope of a short section of bathroom flooring immediately outside the shower to direct water toward the drain. These details were part of the planning process rather than confirmed completed work. The final floor elevations and transitions still required verification against the shower pans and surrounding surfaces.
October 9 Installer Walkthrough and Detailed Field Measurements
On October 9, we completed another site walkthrough with the installation team to confirm the shower dimensions, plumbing locations, and remaining wall preparation. The shower drain connections needed to be coordinated with the pan installation, while a relocated shower valve affected the timing of the surrounding wall work.
We also reviewed the room dimensions and tile layouts. The primary bathroom measured approximately 13 feet 3 inches by 11 feet, the guest bathroom floor about 8 by 7 feet, and the entryway approximately 14 by 7 ½ feet. These measurements helped us coordinate the shower pans, tile installation, and recessed niche locations with the existing layout.
Protecting Hydronic Heating Pipes During Controlled Gypcrete Demolition
Removing the damaged gypcrete required special care because the existing hydronic heating tubing was embedded beneath the tile. During our October 9 review, we planned to remove unstable sections gradually while protecting the exposed heating lines. Working on the fifth floor also required careful preparation before applying self-leveling materials. We needed to seal openings and gaps in the floor assembly to prevent the leveling compound from escaping into the spaces below.
On October 12, we removed the remaining unstable gypcrete from the primary bathroom. The crew cleaned the exposed area thoroughly, skim-coated the shower pan area, and left the remaining floor ready for self-leveling underlayment. While removing the damaged gypcrete around the existing PEX heating lines, we monitored the pressure gauge and observed no pressure loss.
Why the Guest Bathroom Required Additional Gypcrete Removal
The original renovation plan called for extensive gypcrete removal and floor reconstruction in the primary bathroom, while the guest bathroom was expected to need less preparation. However, our October 6 and 9 inspections revealed unstable gypcrete in the guest bathroom as well. Removing the old tile had loosened sections of the existing floor, and exposed hydronic heating pipes required additional care. Rather than installing a new shower assembly over an unstable substrate, we expanded the floor preparation to address the damaged areas.
On October 12, our crew removed the affected gypcrete from the guest shower area and applied self-leveling underlayment. The remaining leveling work was completed on October 13, creating a prepared base for the new shower pan.
Guest Bathroom Drain Misalignment and the Shower Pan Extension
On October 12, the team found that the existing guest shower drain pipe was off-center relative to the intended pan. We reviewed the problem with Tamra and gave her two options. The plumber could relocate the existing drain pipe to match the pan layout, or we could install an additional shower pan extension so the pan assembly could accommodate the existing plumbing location. Tamra chose the extension.
After Tamra selected the pan extension, we installed the guest shower pan on October 13. The extension allowed us to proceed with the planned pan configuration without first relocating the existing drain pipe. The final drain connection and extension details still required verification before waterproofing and tile installation could move forward.
Self-Leveling Underlayment in Both Bathrooms
The primary bathroom required approximately 113.7 square feet of floor preparation outside the shower pan. Our work included cleaning the exposed substrate, protecting adjoining surfaces and openings, and preparing the floor for self-leveling underlayment.
On October 12, the primary bathroom was ready for leveling, while the guest shower area had received its initial application. By October 13, we had completed the self-leveling work in both bathrooms. On October 14, we ground the primary bathroom's leveling compound to prepare the surface for the next membrane installation.
Constructing the Two Curbless Shower Pans
The shower pans were intended to create low-profile floors with the required drainage slope while allowing the finished tile to integrate with the adjacent bathroom floors. The primary shower pan covered approximately 16.7 square feet. On October 12, the primary pan area was skim-coated and ready, and the guest pan base was prepared with a leveling compound. By October 13, we had installed both shower pans, allowing the next stages of floor and waterproofing preparation to move forward.
The pans were in place, but the drain connections, waterproofing details, tile installation, and finished transitions still needed additional work and verification.
HydroBlok Waterproofing, Wall Preparation, and Membranes
The primary bathroom renovation includes approximately 101.4 square feet of planned HydroBlok shower-wall panels extending to the ceiling, with waterproofing around the joints, corners, shower pan, and recessed niche. The relocation of a shower valve affected the surrounding wall preparation, so the installation sequence had to account for the plumbing work before the remaining wall surfaces could be completed.
By October 14, we had completed shower-wall preparation in the guest bathroom, while additional preparation remained in the primary bathroom. That same day, we ground the primary bathroom's leveling compound to prepare it for the planned membrane installation. The guest bathroom had already received its DITRA uncoupling membrane, and the floor was ready for the next preparation stage before tile installation. Final shower waterproofing and testing were still pending.
Planned Tile for the Primary Bathroom, Guest Bathroom, and Entryway
Tamra's primary bathroom design includes new floor and shower tile, tiled wall wainscoting, and a recessed 12-by-24-inch shower niche. During our October 6 walkthrough, we reviewed large-format tile for the shower walls, mosaic flooring, and a possible accent tile for the back of the niche. The final details around the tub pony wall and its edge trim were still under consideration. The guest bathroom will also receive new floor and shower tile, along with tiled wainscoting around the vanity. Tamra was considering a darker tile finish for this bathroom to distinguish it from the primary space.
The entryway renovation calls for approximately 24-by-24-inch porcelain tile over the existing concrete floor, with a DITRA uncoupling membrane beneath the tile. The homeowners' selected materials will be incorporated into the installation as the bathroom and entryway work progresses.
Working in a Fifth-Floor Condominium
Remodeling bathrooms in a fifth-floor condominium required additional planning to protect the residence and surrounding building areas. Our team coordinated material deliveries and access through shared spaces while taking precautions during demolition and floor preparation.
The floor-leveling work required particular attention. Before applying self-leveling compounds, we planned to seal gaps and penetrations that could allow material to escape into spaces below. We also coordinated site protection and daily work arrangements with Tamra to help minimize disruption during construction.
Quality Control and Remaining Adjustments
Throughout the floor reconstruction, we monitored the existing hydronic heating lines and reviewed the preparation work before moving into the next installation stages. During the October 12 gypcrete removal, the pressure gauge showed no loss of pressure in the existing PEX system.
As of October 14, both shower pans were installed, but the bathrooms were not yet ready for final finishes. Our remaining work included verifying the drain connections, completing the primary bathroom's wall and membrane preparation, and coordinating the remaining waterproofing details. The guest bathroom's shower pan extension and the finished-floor transitions also required final review before the project could move into the remaining tile installation stages.
Project Results
By October 14, 2026, we had completed several major preparation stages for Tamra's two curbless showers. Our crew removed unstable gypcrete from the bathroom floors, completed the necessary self-leveling work, and installed both shower pans. The guest bathroom also received its DITRA uncoupling membrane, while preparation continued for the primary bathroom's waterproofing system.
One of the most important parts of the project was rebuilding the floors around the existing hydronic heating lines. During demolition, we monitored the PEX system and observed no pressure loss. In the guest bathroom, we also adapted the shower pan configuration to accommodate the existing off-center drain, following Tamra's decision to use a pan extension rather than relocate the plumbing.
The renovation remains in progress. The next stages include completing the remaining drain connections, waterproofing preparation and verification, and tile installation. Once those stages are finished, our team can move toward the final installation details and homeowner walkthrough.